F2A — All other countries
In the July 2026 Visa Bulletin, F2A for All other countries has a Final Action Dates cut-off of 1 January 2025 and a Dates for Filing cut-off of Current. The Final Action cut-off has been advancing, so the page shows its measured pace and what that pace would imply for a given priority date — as an estimate, never a prediction. This page carries the full published history State printed for this combination: 291 Final Action Dates bulletins back to December 2001, and 130 Dates for Filing bulletins back to October 2015 — every cut-off, every month it moved, and the exact text State printed in each cell. It reports what was published; it is not legal advice.
Source bulletin July 2026 U.S. Department of State, Bureau of Consular Affairs — Visa Bulletin. A work of the U.S. Government, in the public domain (17 U.S.C. §105). Every figure below is the one State printed, kept with its exact source text.
The July 2026 cut-offs
State publishes two charts for F2A, and they are not interchangeable. Both are shown here as printed. This is the All Chargeability Areas Except Those Listed column — it covers every country that does not have a column of its own, which is most of the world. It is not a worldwide figure.
- Final Action Dates
1 January 2025
When a visa can actually be issued. From the July 2026 bulletin · State printed this cell as 01JAN25
- Dates for Filing
Current
When the application may be submitted. From the July 2026 bulletin · State printed this cell as C
This is not legal advice This page republishes cut-off dates exactly as the State Department published them. It cannot tell you what will happen to your case, and being current in a chart is not the same as a visa being issued. Cut-off dates routinely stall, and they can move backward without warning. For advice about your situation, consult a licensed immigration attorney.
Final Action Dates
The chart that decides whether a visa can be issued. State has published a Final Action Dates figure for F2A / All other countries in 291 bulletins since December 2001.
Final Action Dates: when would a priority date be reached?
The cut-off to compare against The Final Action Dates cut-off in the July 2026 bulletin is 1 January 2025. A priority date earlier than that has been reached.
Enter a priority date to compare it against the July 2026 cut-off of 1 January 2025.
Any estimate here is an estimate Estimate only. It projects the cut-off forward at its average pace over the trailing published bulletins and assumes that pace holds. It is not a prediction and not a guarantee: cut-off dates routinely stall, and they can move BACKWARD (retrogress) without warning. Not legal advice.
How fast has this cut-off actually moved?
| Window | Bulletins used | Total movement | Average per month |
|---|---|---|---|
| Last 3 bulletins April 2026 – July 2026 | 3 of 3 carried a measurable move | 335 days forward | about 111.7 days forward |
| Last 6 bulletins January 2026 – July 2026 | 6 of 6 carried a measurable move | 335 days forward | about 55.8 days forward |
| Last 12 bulletins July 2025 – July 2026 | 12 of 12 carried a measurable move | 853 days forward | about 71.1 days forward |
This table describes what already happened; it is not a forecast and it is not what any estimate on this page is computed from. A pace can be zero, or negative when the cut-off has been moving backward, and some windows have nothing measurable in them at all — a category that spent the window Current or Unavailable has no distance to average. A category State has stopped moving can also keep showing a pace from a window that closed years ago, which describes that window and nothing since.
Every published cut-off is on the line above; the table below lists every month it moved.
- Published cut-off date
- Retrogression — the cut-off moved backward (6)
- C — Current: no backlog. Not a date, so it is not on the line
- No bulletin in the public record — the line stops rather than crossing it
| Bulletin | From | To | What changed |
|---|---|---|---|
| June 2026 | 1 August 2024 | 1 January 2025 | Advanced153 days |
| May 2026 | 1 February 2024 | 1 August 2024 | Advanced182 days |
| October 2025 | 1 September 2022 | 1 February 2024 | Advanced518 days |
| July 2025 | 1 January 2022 | 1 September 2022 | Advanced243 days |
| November 2024 | 22 November 2021 | 1 January 2022 | Advanced40 days |
| October 2024 | 15 November 2021 | 22 November 2021 | Advanced7 days |
| June 2024 | 1 June 2021 | 15 November 2021 | Advanced167 days |
| May 2024 | 8 September 2020 | 1 June 2021 | Advanced266 days |
| April 2024 | 22 June 2020 | 8 September 2020 | Advanced78 days |
| March 2024 | 8 February 2020 | 22 June 2020 | Advanced135 days |
| February 2024 | 1 November 2019 | 8 February 2020 | Advanced99 days |
| January 2024 | 8 February 2019 | 1 November 2019 | Advanced266 days |
| October 2023 | 1 January 2018 | 8 February 2019 | Advanced403 days |
| September 2023 | 8 October 2017 | 1 January 2018 | Advanced85 days |
| August 2023 | 8 September 2020 | 8 October 2017 | Retrogressed1,066 days |
| April 2023 | Current | 8 September 2020 | Retrogressed from Current |
| July 2019 | 15 July 2017 | Current | Became Current |
| June 2019 | 15 May 2017 | 15 July 2017 | Advanced61 days |
| May 2019 | 1 March 2017 | 15 May 2017 | Advanced75 days |
| April 2019 | 8 January 2017 | 1 March 2017 | Advanced52 days |
| March 2019 | 1 December 2016 | 8 January 2017 | Advanced38 days |
| February 2019 | 8 November 2016 | 1 December 2016 | Advanced23 days |
| January 2019 | 8 October 2016 | 8 November 2016 | Advanced31 days |
| December 2018 | 15 September 2016 | 8 October 2016 | Advanced23 days |
Show the earlier 181 changes — back to January 2002
| Bulletin | From | To | What changed |
|---|---|---|---|
| November 2018 | 22 August 2016 | 15 September 2016 | Advanced24 days |
| October 2018 | 22 July 2016 | 22 August 2016 | Advanced31 days |
| August 2018 | 22 June 2016 | 22 July 2016 | Advanced30 days |
| July 2018 | 8 June 2016 | 22 June 2016 | Advanced14 days |
| June 2018 | 1 June 2016 | 8 June 2016 | Advanced7 days |
| May 2018 | 1 May 2016 | 1 June 2016 | Advanced31 days |
| April 2018 | 22 March 2016 | 1 May 2016 | Advanced40 days |
| March 2018 | 1 March 2016 | 22 March 2016 | Advanced21 days |
| February 2018 | 1 February 2016 | 1 March 2016 | Advanced29 days |
| January 2018 | 22 December 2015 | 1 February 2016 | Advanced41 days |
| December 2017 | 15 November 2015 | 22 December 2015 | Advanced37 days |
| November 2017 | 22 October 2015 | 15 November 2015 | Advanced24 days |
| October 2017 | 1 October 2015 | 22 October 2015 | Advanced21 days |
| September 2017 | 22 September 2015 | 1 October 2015 | Advanced9 days |
| August 2017 | 8 September 2015 | 22 September 2015 | Advanced14 days |
| July 2017 | 15 August 2015 | 8 September 2015 | Advanced24 days |
| June 2017 | 15 July 2015 | 15 August 2015 | Advanced31 days |
| May 2017 | 8 June 2015 | 15 July 2015 | Advanced37 days |
| April 2017 | 8 May 2015 | 8 June 2015 | Advanced31 days |
| March 2017 | 15 April 2015 | 8 May 2015 | Advanced23 days |
| February 2017 | 22 March 2015 | 15 April 2015 | Advanced24 days |
| January 2017 | 22 February 2015 | 22 March 2015 | Advanced28 days |
| December 2016 | 22 January 2015 | 22 February 2015 | Advanced31 days |
| November 2016 | 22 December 2014 | 22 January 2015 | Advanced31 days |
| October 2016 | 15 November 2014 | 22 December 2014 | Advanced37 days |
| July 2016 | 8 November 2014 | 15 November 2014 | Advanced7 days |
| June 2016 | 1 November 2014 | 8 November 2014 | Advanced7 days |
| May 2016 | 22 October 2014 | 1 November 2014 | Advanced10 days |
| April 2016 | 22 September 2014 | 22 October 2014 | Advanced30 days |
| March 2016 | 1 September 2014 | 22 September 2014 | Advanced21 days |
| February 2016 | 1 August 2014 | 1 September 2014 | Advanced31 days |
| January 2016 | 15 June 2014 | 1 August 2014 | Advanced47 days |
| December 2015 | 15 May 2014 | 15 June 2014 | Advanced31 days |
| November 2015 | 15 April 2014 | 15 May 2014 | Advanced30 days |
| October 2015 | 1 March 2014 | 15 April 2014 | Advanced45 days |
| September 2015 | 15 December 2013 | 1 March 2014 | Advanced76 days |
| August 2015 | 8 November 2013 | 15 December 2013 | Advanced37 days |
| July 2015 | 1 October 2013 | 8 November 2013 | Advanced38 days |
| June 2015 | 1 September 2013 | 1 October 2013 | Advanced30 days |
| May 2015 | 1 August 2013 | 1 September 2013 | Advanced31 days |
| April 2015 | 22 June 2013 | 1 August 2013 | Advanced40 days |
| March 2015 | 8 May 2013 | 22 June 2013 | Advanced45 days |
| February 2015 | 15 April 2013 | 8 May 2013 | Advanced23 days |
| January 2015 | 22 March 2013 | 15 April 2013 | Advanced24 days |
| December 2014 | 1 March 2013 | 22 March 2013 | Advanced21 days |
| November 2014 | 1 February 2013 | 1 March 2013 | Advanced28 days |
| October 2014 | 1 January 2013 | 1 February 2013 | Advanced31 days |
| September 2014 | 1 May 2012 | 1 January 2013 | Advanced245 days |
| June 2014 | 8 September 2013 | 1 May 2012 | Retrogressed495 days |
| October 2013 | Current | 8 September 2013 | Retrogressed from Current |
| August 2013 | 8 October 2011 | Current | Became Current |
| July 2013 | 8 June 2011 | 8 October 2011 | Advanced122 days |
| June 2013 | 1 March 2011 | 8 June 2011 | Advanced99 days |
| May 2013 | 15 December 2010 | 1 March 2011 | Advanced76 days |
| April 2013 | 22 November 2010 | 15 December 2010 | Advanced23 days |
| March 2013 | 22 October 2010 | 22 November 2010 | Advanced31 days |
| February 2013 | 22 September 2010 | 22 October 2010 | Advanced30 days |
| January 2013 | 22 August 2010 | 22 September 2010 | Advanced31 days |
| December 2012 | 15 July 2010 | 22 August 2010 | Advanced38 days |
| November 2012 over 2 months, from the September 2012 bulletin — no bulletin was published for October 2012 | 8 May 2010 | 15 July 2010 | Advanced68 days |
| September 2012 | 15 March 2010 | 8 May 2010 | Advanced54 days |
| August 2012 | 15 February 2010 | 15 March 2010 | Advanced28 days |
| July 2012 | 1 January 2010 | 15 February 2010 | Advanced45 days |
| June 2012 | 15 November 2009 | 1 January 2010 | Advanced47 days |
| May 2012 | 8 October 2009 | 15 November 2009 | Advanced38 days |
| April 2012 | 22 July 2009 | 8 October 2009 | Advanced78 days |
| March 2012 | 8 June 2009 | 22 July 2009 | Advanced44 days |
| February 2012 | 22 April 2009 | 8 June 2009 | Advanced47 days |
| January 2012 | 22 March 2009 | 22 April 2009 | Advanced31 days |
| December 2011 | 15 February 2009 | 22 March 2009 | Advanced35 days |
| November 2011 | 8 January 2009 | 15 February 2009 | Advanced38 days |
| October 2011 | 1 December 2008 | 8 January 2009 | Advanced38 days |
| September 2011 | 22 July 2008 | 1 December 2008 | Advanced132 days |
| August 2011 | 22 March 2008 | 22 July 2008 | Advanced122 days |
| July 2011 | 22 August 2007 | 22 March 2008 | Advanced213 days |
| June 2011 | 8 June 2007 | 22 August 2007 | Advanced75 days |
| May 2011 | 1 April 2007 | 8 June 2007 | Advanced68 days |
| April 2011 | 1 January 2007 | 1 April 2007 | Advanced90 days |
| March 2011 | 1 January 2008 | 1 January 2007 | Retrogressed365 days |
| January 2011 | 1 August 2010 | 1 January 2008 | Retrogressed943 days |
| December 2010 | 1 June 2010 | 1 August 2010 | Advanced61 days |
| November 2010 | 1 April 2010 | 1 June 2010 | Advanced61 days |
| October 2010 | 1 January 2010 | 1 April 2010 | Advanced90 days |
| September 2010 | 1 March 2009 | 1 January 2010 | Advanced306 days |
| August 2010 | 1 July 2008 | 1 March 2009 | Advanced243 days |
| July 2010 | 1 January 2008 | 1 July 2008 | Advanced182 days |
| June 2010 | 1 December 2006 | 1 January 2008 | Advanced396 days |
| May 2010 | 1 June 2006 | 1 December 2006 | Advanced183 days |
| April 2010 | 1 April 2006 | 1 June 2006 | Advanced61 days |
| March 2010 | 1 March 2006 | 1 April 2006 | Advanced31 days |
| February 2010 | 1 January 2006 | 1 March 2006 | Advanced59 days |
| January 2010 | 1 November 2005 | 1 January 2006 | Advanced61 days |
| December 2009 over 4 months, from the August 2009 bulletin — no bulletin was published for September 2009, October 2009, November 2009 | 15 January 2005 | 1 November 2005 | Advanced290 days |
| August 2009 | 22 December 2004 | 15 January 2005 | Advanced24 days |
| July 2009 | 15 December 2004 | 22 December 2004 | Advanced7 days |
| June 2009 | 8 October 2004 | 15 December 2004 | Advanced68 days |
| May 2009 | 15 August 2004 | 8 October 2004 | Advanced54 days |
| April 2009 over 2 months, from the February 2009 bulletin — no bulletin was published for March 2009 | 1 June 2004 | 15 August 2004 | Advanced75 days |
| February 2009 | 15 May 2004 | 1 June 2004 | Advanced17 days |
| January 2009 | 1 April 2004 | 15 May 2004 | Advanced44 days |
| December 2008 | 8 February 2004 | 1 April 2004 | Advanced53 days |
| November 2008 | 1 January 2004 | 8 February 2004 | Advanced38 days |
| October 2008 | 1 December 2003 | 1 January 2004 | Advanced31 days |
| September 2008 | 1 October 2003 | 1 December 2003 | Advanced61 days |
| August 2008 | 1 August 2003 | 1 October 2003 | Advanced61 days |
| July 2008 | 15 July 2003 | 1 August 2003 | Advanced17 days |
| June 2008 | 8 June 2003 | 15 July 2003 | Advanced37 days |
| May 2008 | 8 May 2003 | 8 June 2003 | Advanced31 days |
| April 2008 | 15 April 2003 | 8 May 2003 | Advanced23 days |
| March 2008 | 15 March 2003 | 15 April 2003 | Advanced31 days |
| February 2008 | 22 February 2003 | 15 March 2003 | Advanced21 days |
| January 2008 | 15 January 2003 | 22 February 2003 | Advanced38 days |
| December 2007 | 15 December 2002 | 15 January 2003 | Advanced31 days |
| November 2007 | 15 November 2002 | 15 December 2002 | Advanced30 days |
| October 2007 | 8 October 2002 | 15 November 2002 | Advanced38 days |
| September 2007 | 22 July 2002 | 8 October 2002 | Advanced78 days |
| August 2007 | 1 June 2002 | 22 July 2002 | Advanced51 days |
| July 2007 | 22 April 2002 | 1 June 2002 | Advanced40 days |
| June 2007 | 8 April 2002 | 22 April 2002 | Advanced14 days |
| May 2007 | 1 April 2002 | 8 April 2002 | Advanced7 days |
| April 2007 | 22 March 2002 | 1 April 2002 | Advanced10 days |
| February 2007 | 15 March 2002 | 22 March 2002 | Advanced7 days |
| January 2007 | 1 March 2002 | 15 March 2002 | Advanced14 days |
| December 2006 | 1 September 2001 | 1 March 2002 | Advanced181 days |
| November 2006 | 22 April 2001 | 1 September 2001 | Advanced132 days |
| October 2006 | 22 September 1999 | 22 April 2001 | Advanced578 days |
| September 2006 | 8 September 1999 | 22 September 1999 | Advanced14 days |
| August 2006 | 1 September 1999 | 8 September 1999 | Advanced7 days |
| July 2006 | 22 April 2001 | 1 September 1999 | Retrogressed599 days |
| June 2006 | 1 March 2002 | 22 April 2001 | Retrogressed313 days |
| April 2006 | 22 February 2002 | 1 March 2002 | Advanced7 days |
| March 2006 | 8 February 2002 | 22 February 2002 | Advanced14 days |
| February 2006 | 15 January 2002 | 8 February 2002 | Advanced24 days |
| January 2006 | 1 January 2002 | 15 January 2002 | Advanced14 days |
| December 2005 | 1 December 2001 | 1 January 2002 | Advanced31 days |
| November 2005 | 1 November 2001 | 1 December 2001 | Advanced30 days |
| October 2005 | 22 September 2001 | 1 November 2001 | Advanced40 days |
| September 2005 | 22 July 2001 | 22 September 2001 | Advanced62 days |
| August 2005 | 22 May 2001 | 22 July 2001 | Advanced61 days |
| July 2005 | 22 April 2001 | 22 May 2001 | Advanced30 days |
| June 2005 | 1 March 2001 | 22 April 2001 | Advanced52 days |
| May 2005 | 8 January 2001 | 1 March 2001 | Advanced52 days |
| April 2005 | 15 November 2000 | 8 January 2001 | Advanced54 days |
| March 2005 | 1 October 2000 | 15 November 2000 | Advanced45 days |
| February 2005 | 15 August 2000 | 1 October 2000 | Advanced47 days |
| January 2005 | 1 July 2000 | 15 August 2000 | Advanced45 days |
| December 2004 | 1 June 2000 | 1 July 2000 | Advanced30 days |
| November 2004 | 1 May 2000 | 1 June 2000 | Advanced31 days |
| October 2004 | 15 April 2000 | 1 May 2000 | Advanced16 days |
| August 2004 | 1 March 2000 | 15 April 2000 | Advanced45 days |
| July 2004 | 8 December 1999 | 1 March 2000 | Advanced84 days |
| June 2004 | 15 October 1999 | 8 December 1999 | Advanced54 days |
| May 2004 | 15 July 1999 | 15 October 1999 | Advanced92 days |
| April 2004 | 15 May 1999 | 15 July 1999 | Advanced61 days |
| March 2004 | 1 March 1999 | 15 May 1999 | Advanced75 days |
| February 2004 | 1 January 1999 | 1 March 1999 | Advanced59 days |
| January 2004 | 15 November 1998 | 1 January 1999 | Advanced47 days |
| December 2003 | 8 October 1998 | 15 November 1998 | Advanced38 days |
| November 2003 | 15 September 1998 | 8 October 1998 | Advanced23 days |
| October 2003 | 15 August 1998 | 15 September 1998 | Advanced31 days |
| September 2003 | 1 July 1998 | 15 August 1998 | Advanced45 days |
| August 2003 | 15 May 1998 | 1 July 1998 | Advanced47 days |
| July 2003 | 15 April 1998 | 15 May 1998 | Advanced30 days |
| June 2003 | 15 March 1998 | 15 April 1998 | Advanced31 days |
| May 2003 | 1 February 1998 | 15 March 1998 | Advanced42 days |
| April 2003 | 8 December 1997 | 1 February 1998 | Advanced55 days |
| March 2003 | 15 November 1997 | 8 December 1997 | Advanced23 days |
| February 2003 | 22 October 1997 | 15 November 1997 | Advanced24 days |
| January 2003 | 22 September 1997 | 22 October 1997 | Advanced30 days |
| December 2002 | 15 August 1997 | 22 September 1997 | Advanced38 days |
| November 2002 | 15 July 1997 | 15 August 1997 | Advanced31 days |
| October 2002 | 15 June 1997 | 15 July 1997 | Advanced30 days |
| September 2002 | 15 May 1997 | 15 June 1997 | Advanced31 days |
| August 2002 | 15 April 1997 | 15 May 1997 | Advanced30 days |
| July 2002 | 1 March 1997 | 15 April 1997 | Advanced45 days |
| June 2002 | 15 January 1997 | 1 March 1997 | Advanced45 days |
| May 2002 | 8 December 1996 | 15 January 1997 | Advanced38 days |
| April 2002 | 15 November 1996 | 8 December 1996 | Advanced23 days |
| March 2002 | 22 October 1996 | 15 November 1996 | Advanced24 days |
| February 2002 | 1 October 1996 | 22 October 1996 | Advanced21 days |
| January 2002 | 22 September 1996 | 1 October 1996 | Advanced9 days |
Dates for Filing
The chart that decides when an application may be submitted — usually the more optimistic of the two. It did not exist before October 2015, so its history is shorter by design, not by omission: 130 bulletins since October 2015.
Dates for Filing: when would a priority date be reached?
The answer for every priority date This category is Current in the July 2026 bulletin. There is no backlog and no cut-off to wait for, so every priority date in it is being acted on now. This category is CURRENT in the newest bulletin: there is no backlog, so any priority date is current now. No projection is needed.
How fast has this cut-off actually moved?
| Window | Bulletins used | Total movement | Average per month |
|---|---|---|---|
| Last 3 bulletins April 2026 – July 2026 | 0 of 3 carried a measurable move | nothing measurable | not measurable |
| Last 6 bulletins January 2026 – July 2026 | 2 of 6 carried a measurable move | 62 days forward | about 31 days forward |
| Last 12 bulletins July 2025 – July 2026 | 8 of 12 carried a measurable move | 358 days forward | about 44.8 days forward |
This table describes what already happened; it is not a forecast and it is not what any estimate on this page is computed from. A pace can be zero, or negative when the cut-off has been moving backward, and some windows have nothing measurable in them at all — a category that spent the window Current or Unavailable has no distance to average. A category State has stopped moving can also keep showing a pace from a window that closed years ago, which describes that window and nothing since.
Every published cut-off is on the line above; the table below lists every month it moved.
- Published cut-off date
- C — Current: no backlog. Not a date, so it is not on the line
| Bulletin | From | To | What changed |
|---|---|---|---|
| April 2026 | 22 February 2026 | Current | Became Current |
| March 2026 | 22 January 2026 | 22 February 2026 | Advanced31 days |
| February 2026 | 22 December 2025 | 22 January 2026 | Advanced31 days |
| January 2026 | 22 November 2025 | 22 December 2025 | Advanced30 days |
| December 2025 | 22 October 2025 | 22 November 2025 | Advanced31 days |
| November 2025 | 22 September 2025 | 22 October 2025 | Advanced30 days |
| October 2025 | 1 June 2025 | 22 September 2025 | Advanced113 days |
| September 2025 | 1 April 2025 | 1 June 2025 | Advanced61 days |
| August 2025 | 1 March 2025 | 1 April 2025 | Advanced31 days |
| July 2025 | 1 February 2025 | 1 March 2025 | Advanced28 days |
| May 2025 | 15 October 2024 | 1 February 2025 | Advanced109 days |
| April 2025 | 15 July 2024 | 15 October 2024 | Advanced92 days |
| October 2024 | 15 June 2024 | 15 July 2024 | Advanced30 days |
| August 2024 | 1 November 2023 | 15 June 2024 | Advanced227 days |
| July 2024 | 1 September 2023 | 1 November 2023 | Advanced61 days |
| September 2023 | Current | 1 September 2023 | Retrogressed from Current |
| April 2022 | 1 December 2021 | Current | Became Current |
| March 2022 | 1 October 2021 | 1 December 2021 | Advanced61 days |
| January 2022 | 1 September 2021 | 1 October 2021 | Advanced30 days |
| December 2021 | 1 June 2021 | 1 September 2021 | Advanced92 days |
| July 2021 | 1 May 2021 | 1 June 2021 | Advanced31 days |
| June 2021 | 1 April 2021 | 1 May 2021 | Advanced30 days |
| May 2021 | 1 March 2021 | 1 April 2021 | Advanced31 days |
| April 2021 | 1 February 2021 | 1 March 2021 | Advanced28 days |
Show the earlier 29 changes — back to October 2015
| Bulletin | From | To | What changed |
|---|---|---|---|
| March 2021 | 1 January 2021 | 1 February 2021 | Advanced31 days |
| February 2021 | 1 August 2020 | 1 January 2021 | Advanced153 days |
| September 2020 | 1 July 2020 | 1 August 2020 | Advanced31 days |
| August 2020 | 1 June 2020 | 1 July 2020 | Advanced30 days |
| July 2020 | 1 May 2020 | 1 June 2020 | Advanced31 days |
| June 2020 | 1 March 2020 | 1 May 2020 | Advanced61 days |
| May 2020 | 1 February 2020 | 1 March 2020 | Advanced29 days |
| April 2020 | 1 January 2020 | 1 February 2020 | Advanced31 days |
| March 2020 | 1 December 2019 | 1 January 2020 | Advanced31 days |
| February 2020 | 1 November 2019 | 1 December 2019 | Advanced30 days |
| January 2020 | 1 October 2019 | 1 November 2019 | Advanced31 days |
| December 2019 | 1 September 2019 | 1 October 2019 | Advanced30 days |
| November 2019 | 1 August 2019 | 1 September 2019 | Advanced31 days |
| October 2019 | 1 July 2019 | 1 August 2019 | Advanced31 days |
| September 2019 | 1 June 2019 | 1 July 2019 | Advanced30 days |
| August 2019 | 8 March 2019 | 1 June 2019 | Advanced85 days |
| June 2019 | 8 January 2018 | 8 March 2019 | Advanced424 days |
| May 2019 | 15 December 2017 | 8 January 2018 | Advanced24 days |
| April 2019 | 8 December 2017 | 15 December 2017 | Advanced7 days |
| March 2019 | 1 December 2017 | 8 December 2017 | Advanced7 days |
| July 2018 | 22 September 2017 | 1 December 2017 | Advanced70 days |
| April 2018 | 1 May 2017 | 22 September 2017 | Advanced144 days |
| March 2018 | 1 November 2016 | 1 May 2017 | Advanced181 days |
| October 2017 | 8 April 2016 | 1 November 2016 | Advanced207 days |
| May 2017 | 22 November 2015 | 8 April 2016 | Advanced138 days |
| August 2016 | 15 October 2015 | 22 November 2015 | Advanced38 days |
| June 2016 | 15 June 2015 | 15 October 2015 | Advanced122 days |
| January 2016 | 1 March 2015 | 15 June 2015 | Advanced106 days |
| October 2015 | not published | 1 March 2015 | First published |
How to read this page
What a priority date is
A priority date is the date that fixes your place in the queue for an immigrant visa number. For most family-sponsored categories it is the date the petition was filed; for employment-based categories that require labour certification, it is the date that certification was filed. It is printed on the I-797 receipt or approval notice. Your priority date does not move — the cut-off moves toward it.
Congress caps how many immigrant visas may be issued each year, both in total per category and per country of chargeability. When more people want a category than the cap allows, a queue forms, and State publishes a cut-off date each month: the priority date it has reached. If your priority date is earlier than the cut-off, your turn has come in that chart.
Why All other countries has its own column
This page is the column State prints as "All Chargeability Areas Except Those Listed". It is the queue for every country that does not have its own column — not a global average, and not everyone. A country gets its own column only when demand from applicants chargeable to it exceeds the per-country limit; in the July 2026 bulletin those are China (mainland-born), India, Mexico and the Philippines. If your country of chargeability is not one of those, this column is the one that applies to you.
The two charts are not interchangeable
Final Action Dates is when a visa can actually be issued or a green card approved. Dates for Filing is when the application may be submitted; it is usually the earlier and more optimistic of the two, and being past it does not mean a visa can be issued. Which chart U.S. Citizenship and Immigration Services will accept for adjustment-of-status filings is announced by USCIS each month and is not decided by State or by this site. The Dates for Filing chart was introduced in October 2015 and does not exist for any earlier bulletin.
What Current and Unavailable mean
Current (printed C) means there is no backlog at all: every priority date in the category is being acted on. Unavailable (printed U) means no visas are being issued in the category at all that month — usually because the annual limit has been reached. Neither is a date, and neither can be compared to one, so this site never plots them on a date axis and never projects from them.
Retrogression: the cut-off can move backward
A cut-off is not a promise and does not only move forward. When more people apply than the annual limit allows — often after a period of rapid advancement draws in filings — State pulls the cut-off back to an earlier date. This is called retrogression, and it can undo years of progress in a single bulletin. It has happened 359 times across the whole published record this site holds. The largest on record is F3 for Mexico in August 2006, which moved back 12.79 years in one month. Retrogressions on this page are marked on the chart with a ▼ mark and listed in the movement tables with a ↓ glyph — never by colour alone.
Where F2A sits among the family preferences
Family-sponsored preference categories run F1 through F4, and they are separate queues with separate annual limits: F1 (unmarried adult sons and daughters of U.S. citizens), F2A (spouses and minor children of lawful permanent residents), F2B (unmarried adult sons and daughters of permanent residents), F3 (married sons and daughters of U.S. citizens) and F4 (brothers and sisters of adult U.S. citizens). Immediate relatives of U.S. citizens — spouses, minor children and parents — are not subject to these limits and do not appear in the Visa Bulletin at all.
Frequently asked questions
- What is the F2A priority date cut-off for All other countries in the July 2026 Visa Bulletin?
- The Final Action Dates cut-off is 1 January 2025 and the Dates for Filing cut-off is Current. State printed those cells as "01JAN25" and "C". A priority date earlier than 1 January 2025 has been reached in the Final Action chart.
- What is the difference between Final Action Dates and Dates for Filing for F2A?
- They answer different questions and they are not interchangeable. Final Action Dates is when a visa can actually be issued or a green card approved. Dates for Filing is when the application may be submitted — it is usually the earlier and more optimistic of the two, and being past it does not mean a visa can be issued. For F2A and All other countries in the July 2026 bulletin they read 1 January 2025 and Current respectively. Which chart U.S. Citizenship and Immigration Services accepts for adjustment-of-status filings is announced by USCIS each month and is not decided by this site. The Dates for Filing chart did not exist before October 2015.
- What is a priority date?
- A priority date is the date that fixes your place in the queue for a visa number. For most family-sponsored and employment-based categories it is the date the petition was filed with the government (for employment categories requiring labour certification, it is the date that certification was filed). It is printed on the I-797 receipt or approval notice. The Visa Bulletin publishes a cut-off date each month for each category and country of chargeability; if your priority date is earlier than the cut-off, your turn has come in that chart. Your priority date never changes on its own — the cut-off moves toward it.
- Has the F2A cut-off for All other countries ever moved backward?
- Yes. Moving backward is called retrogression, and it happens when more people apply in a category than the annual limit allows, forcing State to pull the cut-off back to an earlier date. This combination has retrogressed 9 times in the published record — 8 in the Final Action Dates chart and 1 in the Dates for Filing chart. The largest was in August 2023, when the Final Action cut-off moved back from 8 September 2020 to 8 October 2017 — 1,066 days, or about 2.9 years, in a single bulletin.
- When will a priority date in F2A become current for All other countries?
- Nobody can tell you that, and this site does not claim to. What can be measured is the pace: over the trailing published bulletins the Final Action Dates cut-off has advanced by an average of about 71.1 days per bulletin. The tool on this page projects the published cut-off of 1 January 2025 forward at that pace to estimate which bulletin would reach a given priority date. That is an estimate and assumes the pace holds. It is not a prediction and not a guarantee: cut-off dates routinely stall, and they can move backward without warning. This is not legal advice.
- Where does this F2A history come from, and how far back does it go?
- Every figure is the one the U.S. Department of State printed in its monthly Visa Bulletin, kept alongside the exact cell text it came from. This page carries 291 Final Action Dates bulletins back to December 2001 and 130 Dates for Filing bulletins back to October 2015. The Visa Bulletin is a work of the U.S. Government and is in the public domain (17 U.S.C. section 105). 5 months are absent from the public record in that span (March 2009, September 2009, October 2009, November 2009, October 2012); they are shown as a break in the chart and are never filled in from a neighbouring month.
Source and method
Every figure on this page is read from the U.S. Department of State's monthly Visa Bulletin — the July 2026 edition for the current cut-offs, and each bulletin's own edition for the history. The Visa Bulletin is a work of the U.S. Government prepared by federal employees in the course of their duties, and is therefore in the public domain under 17 U.S.C. §105. This site is not affiliated with, endorsed by, or connected to the U.S. Department of State or any government agency.
This page carries 421 published cut-off cells for F2A / All other countries and 258 recorded changes across both charts. Each cell is stored with the exact text State printed for it (the 01JAN25 shown above is the source's own), so every figure here is traceable back to the bulletin it came from.
5 months in the December 2001 to July 2026 span are absent from the public record — March 2009, September 2009, October 2009, November 2009, October 2012. They are recorded as gaps and shown as breaks in the charts above, never filled in from a neighbouring month.
Data version visa-bulletin-derived-v1 · 291 bulletins, December 2001 to July 2026 · Next monthly bulletin. The State Department publishes one bulletin per month, typically mid-month for the following month; past bulletins are immutable once published.