Other Workers — China (mainland-born)
In the August 2026 Visa Bulletin, Other Workers for China (mainland-born) has a Final Action Dates cut-off of 1 May 2019 and no Dates for Filing chart published this bulletin. The Final Action cut-off has been advancing, so the page shows its measured pace and what that pace would imply for a given priority date — as an estimate, never a prediction. This page carries the full published history State printed for this combination: 255 Final Action Dates bulletins back to January 2005, and 130 Dates for Filing bulletins back to October 2015 — every cut-off, every month it moved, and the exact text State printed in each cell. It reports what was published; it is not legal advice.
Source bulletin August 2026 U.S. Department of State, Bureau of Consular Affairs — Visa Bulletin. A work of the U.S. Government, in the public domain (17 U.S.C. §105). Every figure below is the one State printed, kept with its exact source text.
The August 2026 cut-offs
State publishes two charts for Other Workers, and they are not interchangeable. Both are shown here as printed. China (mainland-born) has its own column because demand from applicants chargeable there exceeds the per-country limit, so its cut-offs are usually further behind than the "all other countries" column.
- Final Action Dates
1 May 2019
When a visa can actually be issued. From the August 2026 bulletin · State printed this cell as 01MAY19
- Dates for Filing
Not published
Not part of the August 2026 bulletin's published source.
This is not legal advice This page republishes cut-off dates exactly as the State Department published them. It cannot tell you what will happen to your case, and being current in a chart is not the same as a visa being issued. Cut-off dates routinely stall, and they can move backward without warning. For advice about your situation, consult a licensed immigration attorney.
Final Action Dates
The chart that decides whether a visa can be issued. State has published a Final Action Dates figure for Other Workers / China (mainland-born) in 255 bulletins since January 2005.
Final Action Dates: when would a priority date be reached?
The cut-off to compare against The Final Action Dates cut-off in the August 2026 bulletin is 1 May 2019. A priority date earlier than that has been reached.
Enter a priority date to compare it against the August 2026 cut-off of 1 May 2019.
Any estimate here is an estimate Estimate only. It projects the cut-off forward at its average pace over the trailing published bulletins and assumes that pace holds. It is not a prediction and not a guarantee: cut-off dates routinely stall, and they can move BACKWARD (retrogress) without warning. Not legal advice.
How fast has this cut-off actually moved?
| Window | Bulletins used | Total movement | Average per month |
|---|---|---|---|
| Last 3 bulletins May 2026 – August 2026 | 3 of 3 carried a measurable move | 89 days forward | about 29.7 days forward |
| Last 6 bulletins February 2026 – August 2026 | 6 of 6 carried a measurable move | 144 days forward | about 24 days forward |
| Last 12 bulletins August 2025 – August 2026 | 12 of 12 carried a measurable move | 730 days forward | about 60.8 days forward |
This table describes what already happened; it is not a forecast and it is not what any estimate on this page is computed from. A pace can be zero, or negative when the cut-off has been moving backward, and some windows have nothing measurable in them at all — a category that spent the window Current or Unavailable has no distance to average. A category State has stopped moving can also keep showing a pace from a window that closed years ago, which describes that window and nothing since.
Every published cut-off is on the line above; the table below lists every month it moved.
- Published cut-off date
- Retrogression — the cut-off moved backward (8)
- C — Current: no backlog. Not a date, so it is not on the line
- U — Unavailable: no visas issued. Not a date either
- No bulletin in the public record — the line stops rather than crossing it
| Bulletin | From | To | What changed |
|---|---|---|---|
| August 2026 | 1 April 2019 | 1 May 2019 | Advanced30 days |
| June 2026 | 1 February 2019 | 1 April 2019 | Advanced59 days |
| April 2026 | 8 December 2018 | 1 February 2019 | Advanced55 days |
| January 2026 | 8 December 2017 | 8 December 2018 | Advanced365 days |
| December 2025 | 1 December 2017 | 8 December 2017 | Advanced7 days |
| October 2025 | 1 May 2017 | 1 December 2017 | Advanced214 days |
| July 2025 | 1 April 2017 | 1 May 2017 | Advanced30 days |
| April 2025 | 1 January 2017 | 1 April 2017 | Advanced90 days |
| January 2024 | 1 January 2016 | 1 January 2017 | Advanced366 days |
| October 2023 | 1 September 2015 | 1 January 2016 | Advanced122 days |
| June 2023 | 15 April 2015 | 1 September 2015 | Advanced139 days |
| May 2023 | 1 October 2014 | 15 April 2015 | Advanced196 days |
| April 2023 | 1 July 2014 | 1 October 2014 | Advanced92 days |
| March 2023 | 22 December 2013 | 1 July 2014 | Advanced191 days |
| January 2023 | 22 June 2013 | 22 December 2013 | Advanced183 days |
| December 2022 | 1 December 2012 | 22 June 2013 | Advanced203 days |
| November 2022 | 1 September 2012 | 1 December 2012 | Advanced91 days |
| October 2022 | 1 June 2012 | 1 September 2012 | Advanced92 days |
| April 2022 | 1 May 2012 | 1 June 2012 | Advanced31 days |
| March 2022 | 1 April 2012 | 1 May 2012 | Advanced30 days |
| February 2022 | 1 March 2012 | 1 April 2012 | Advanced31 days |
| December 2021 | 1 March 2010 | 1 March 2012 | Advanced731 days |
| November 2021 | 1 February 2010 | 1 March 2010 | Advanced28 days |
| September 2021 | 1 January 2010 | 1 February 2010 | Advanced31 days |
Show the earlier 106 changes — back to January 2005
| Bulletin | From | To | What changed |
|---|---|---|---|
| August 2021 | 1 December 2009 | 1 January 2010 | Advanced31 days |
| July 2021 | 1 October 2009 | 1 December 2009 | Advanced61 days |
| June 2021 | 1 August 2009 | 1 October 2009 | Advanced61 days |
| May 2021 | 1 June 2009 | 1 August 2009 | Advanced61 days |
| April 2021 | 1 May 2009 | 1 June 2009 | Advanced31 days |
| March 2021 | 1 April 2009 | 1 May 2009 | Advanced30 days |
| February 2021 | 1 March 2009 | 1 April 2009 | Advanced31 days |
| January 2021 | 15 February 2009 | 1 March 2009 | Advanced14 days |
| December 2020 | 1 January 2009 | 15 February 2009 | Advanced45 days |
| November 2020 | 1 December 2008 | 1 January 2009 | Advanced31 days |
| October 2020 | 1 August 2008 | 1 December 2008 | Advanced122 days |
| August 2020 | 22 July 2008 | 1 August 2008 | Advanced10 days |
| July 2020 | 15 July 2008 | 22 July 2008 | Advanced7 days |
| May 2020 | 1 July 2008 | 15 July 2008 | Advanced14 days |
| April 2020 | 1 June 2008 | 1 July 2008 | Advanced30 days |
| March 2020 | 1 May 2008 | 1 June 2008 | Advanced31 days |
| February 2020 | 1 April 2008 | 1 May 2008 | Advanced30 days |
| January 2020 | 1 March 2008 | 1 April 2008 | Advanced31 days |
| December 2019 | 1 February 2008 | 1 March 2008 | Advanced29 days |
| November 2019 | 1 January 2008 | 1 February 2008 | Advanced31 days |
| October 2019 | 22 November 2007 | 1 January 2008 | Advanced40 days |
| July 2019 | 1 September 2007 | 22 November 2007 | Advanced82 days |
| May 2019 | 22 August 2007 | 1 September 2007 | Advanced10 days |
| April 2019 | 15 August 2007 | 22 August 2007 | Advanced7 days |
| March 2019 | 1 August 2007 | 15 August 2007 | Advanced14 days |
| February 2019 | 1 July 2007 | 1 August 2007 | Advanced31 days |
| January 2019 | 1 June 2007 | 1 July 2007 | Advanced30 days |
| December 2018 | 1 May 2007 | 1 June 2007 | Advanced31 days |
| May 2018 | 1 April 2007 | 1 May 2007 | Advanced30 days |
| April 2018 | 1 March 2007 | 1 April 2007 | Advanced31 days |
| March 2018 | 1 February 2007 | 1 March 2007 | Advanced28 days |
| February 2018 | 22 December 2006 | 1 February 2007 | Advanced41 days |
| January 2018 | 1 July 2006 | 22 December 2006 | Advanced174 days |
| December 2017 | 1 April 2006 | 1 July 2006 | Advanced91 days |
| November 2017 | 1 January 2006 | 1 April 2006 | Advanced90 days |
| October 2017 | 1 January 2004 | 1 January 2006 | Advanced731 days |
| August 2017 | 15 July 2006 | 1 January 2004 | Retrogressed926 days |
| June 2017 | 8 March 2006 | 15 July 2006 | Advanced129 days |
| May 2017 | 1 March 2006 | 8 March 2006 | Advanced7 days |
| April 2017 | 1 February 2006 | 1 March 2006 | Advanced28 days |
| March 2017 | 1 December 2005 | 1 February 2006 | Advanced62 days |
| January 2017 | 1 November 2005 | 1 December 2005 | Advanced30 days |
| December 2016 | 1 September 2005 | 1 November 2005 | Advanced61 days |
| November 2016 | 1 January 2005 | 1 September 2005 | Advanced243 days |
| October 2016 | 1 January 2004 | 1 January 2005 | Advanced366 days |
| July 2016 | 22 April 2007 | 1 January 2004 | Retrogressed1,207 days |
| May 2016 | 1 March 2007 | 22 April 2007 | Advanced52 days |
| April 2016 | 1 February 2007 | 1 March 2007 | Advanced28 days |
| March 2016 | 22 December 2006 | 1 February 2007 | Advanced41 days |
| February 2016 | 1 December 2006 | 22 December 2006 | Advanced21 days |
| January 2016 | 1 August 2006 | 1 December 2006 | Advanced122 days |
| December 2015 | 1 April 2006 | 1 August 2006 | Advanced122 days |
| November 2015 | 1 January 2006 | 1 April 2006 | Advanced90 days |
| October 2015 | 1 January 2004 | 1 January 2006 | Advanced731 days |
| August 2015 | 1 January 2006 | 1 January 2004 | Retrogressed731 days |
| June 2015 | 15 November 2005 | 1 January 2006 | Advanced47 days |
| May 2015 | 15 August 2005 | 15 November 2005 | Advanced92 days |
| February 2015 | 22 July 2005 | 15 August 2005 | Advanced24 days |
| August 2014 | 1 January 2003 | 22 July 2005 | Advanced933 days |
| June 2014 | 1 October 2012 | 1 January 2003 | Retrogressed3,561 days |
| April 2014 | 1 September 2012 | 1 October 2012 | Advanced30 days |
| March 2014 | 1 June 2012 | 1 September 2012 | Advanced92 days |
| February 2014 | 1 April 2012 | 1 June 2012 | Advanced61 days |
| January 2014 | 1 October 2011 | 1 April 2012 | Advanced183 days |
| December 2013 | 1 October 2010 | 1 October 2011 | Advanced365 days |
| November 2013 | 22 September 2004 | 1 October 2010 | Advanced2,200 days |
| October 2013 | 15 June 2004 | 22 September 2004 | Advanced99 days |
| September 2013 | 22 March 2004 | 15 June 2004 | Advanced85 days |
| July 2013 | 22 October 2003 | 22 March 2004 | Advanced152 days |
| June 2013 | 1 September 2003 | 22 October 2003 | Advanced51 days |
| May 2013 | 1 August 2003 | 1 September 2003 | Advanced31 days |
| April 2013 | 1 July 2003 | 1 August 2003 | Advanced31 days |
| November 2012 over 2 months, from the September 2012 bulletin — no bulletin was published for October 2012 | 22 June 2003 | 1 July 2003 | Advanced9 days |
| September 2012 | 15 June 2003 | 22 June 2003 | Advanced7 days |
| July 2012 | 22 April 2003 | 15 June 2003 | Advanced54 days |
| December 2010 | 1 April 2003 | 22 April 2003 | Advanced21 days |
| November 2010 | 22 March 2003 | 1 April 2003 | Advanced10 days |
| September 2010 | 15 May 2002 | 22 March 2003 | Advanced311 days |
| August 2010 | 1 June 2001 | 15 May 2002 | Advanced348 days |
| December 2009 over 4 months, from the August 2009 bulletin — no bulletin was published for September 2009, October 2009, November 2009 | Unavailable | 1 June 2001 | Became available again |
| May 2009 | 1 March 2001 | Unavailable | Became Unavailable |
| April 2009 over 2 months, from the February 2009 bulletin — no bulletin was published for March 2009 | 1 October 2002 | 1 March 2001 | Retrogressed579 days |
| February 2009 | 15 March 2003 | 1 October 2002 | Retrogressed165 days |
| January 2009 | 15 January 2003 | 15 March 2003 | Advanced59 days |
| November 2008 | 1 January 2003 | 15 January 2003 | Advanced14 days |
| October 2008 | Unavailable | 1 January 2003 | Became available again |
| August 2008 | 1 January 2003 | Unavailable | Became Unavailable |
| May 2008 | 1 March 2002 | 1 January 2003 | Advanced306 days |
| April 2008 | 1 January 2002 | 1 March 2002 | Advanced59 days |
| March 2008 | 1 October 2001 | 1 January 2002 | Advanced92 days |
| October 2007 | Unavailable | 1 October 2001 | Became available again |
| July 2007 | 1 October 2001 | Unavailable | Became Unavailable |
| June 2007 | Unavailable | 1 October 2001 | Became available again |
| May 2007 | 1 October 2001 | Unavailable | Became Unavailable |
| December 2006 | 1 May 2001 | 1 October 2001 | Advanced153 days |
| November 2006 | 1 January 2001 | 1 May 2001 | Advanced120 days |
| October 2006 | Unavailable | 1 January 2001 | Became available again |
| June 2006 | 1 October 2000 | Unavailable | Became Unavailable |
| May 2006 | 1 October 2001 | 1 October 2000 | Retrogressed365 days |
| February 2006 | 1 April 2001 | 1 October 2001 | Advanced183 days |
| January 2006 | 1 October 2000 | 1 April 2001 | Advanced182 days |
| October 2005 | Unavailable | 1 October 2000 | Became available again |
| July 2005 | 1 January 1999 | Unavailable | Became Unavailable |
| June 2005 | 1 July 2001 | 1 January 1999 | Retrogressed912 days |
| March 2005 | Current | 1 July 2001 | Retrogressed from Current |
| January 2005 | not published | Current | First published |
Dates for Filing
State did not publish a Dates for Filing figure for Other Workers / China (mainland-born) in the August 2026 bulletin — this month's source ( preference) carries only one of the two charts. This chart's published history will return once a bulletin carrying it is available again.
How to read this page
What a priority date is
A priority date is the date that fixes your place in the queue for an immigrant visa number. For most family-sponsored categories it is the date the petition was filed; for employment-based categories that require labour certification, it is the date that certification was filed. It is printed on the I-797 receipt or approval notice. Your priority date does not move — the cut-off moves toward it.
Congress caps how many immigrant visas may be issued each year, both in total per category and per country of chargeability. When more people want a category than the cap allows, a queue forms, and State publishes a cut-off date each month: the priority date it has reached. If your priority date is earlier than the cut-off, your turn has come in that chart.
Chargeability, and why some countries have their own column
Chargeability is normally your country of birth — not your citizenship or where you live. A country gets its own column in the bulletin only when demand from applicants chargeable to it exceeds the per-country limit; in the August 2026 bulletin those are China (mainland-born), India, Mexico and the Philippines. Everyone else is counted together in the column State prints as "All Chargeability Areas Except Those Listed", which is not a global average and not a worldwide figure.
The two charts are not interchangeable
Final Action Dates is when a visa can actually be issued or a green card approved. Dates for Filing is when the application may be submitted; it is usually the earlier and more optimistic of the two, and being past it does not mean a visa can be issued. Which chart U.S. Citizenship and Immigration Services will accept for adjustment-of-status filings is announced by USCIS each month and is not decided by State or by this site. The Dates for Filing chart was introduced in October 2015 and does not exist for any earlier bulletin.
What Current and Unavailable mean
Current (printed C) means there is no backlog at all: every priority date in the category is being acted on. Unavailable (printed U) means no visas are being issued in the category at all that month — usually because the annual limit has been reached. Neither is a date, and neither can be compared to one, so this site never plots them on a date axis and never projects from them.
Retrogression: the cut-off can move backward
A cut-off is not a promise and does not only move forward. When more people apply than the annual limit allows — often after a period of rapid advancement draws in filings — State pulls the cut-off back to an earlier date. This is called retrogression, and it can undo years of progress in a single bulletin. It has happened 359 times across the whole published record this site holds. The largest on record is F3 for Mexico in August 2006, which moved back 12.79 years in one month. Retrogressions on this page are marked on the chart with a ▼ mark and listed in the movement tables with a ↓ glyph — never by colour alone.
Frequently asked questions
- What is the Other Workers priority date cut-off for China (mainland-born) in the August 2026 Visa Bulletin?
- The Final Action Dates cut-off is 1 May 2019. State printed that cell as "01MAY19". A priority date earlier than 1 May 2019 has been reached in the Final Action Dates chart. The Dates for Filing chart is not part of this bulletin's published source this month (see Source and method, below); this page will show it again once a bulletin carrying it is available.
- What is the difference between Final Action Dates and Dates for Filing for Other Workers?
- They answer different questions and they are not interchangeable. Final Action Dates is when a visa can actually be issued or a green card approved. Dates for Filing is when the application may be submitted — it is usually the earlier and more optimistic of the two, and being past it does not mean a visa can be issued. This month's source publishes only the Final Action Dates chart for this combination, so only that figure is shown above. Which chart U.S. Citizenship and Immigration Services accepts for adjustment-of-status filings is announced by USCIS each month and is not decided by this site. The Dates for Filing chart did not exist before October 2015.
- What is a priority date?
- A priority date is the date that fixes your place in the queue for a visa number. For most family-sponsored and employment-based categories it is the date the petition was filed with the government (for employment categories requiring labour certification, it is the date that certification was filed). It is printed on the I-797 receipt or approval notice. The Visa Bulletin publishes a cut-off date each month for each category and country of chargeability; if your priority date is earlier than the cut-off, your turn has come in that chart. Your priority date never changes on its own — the cut-off moves toward it.
- Has the Other Workers Final Action Dates cut-off for China (mainland-born) ever moved backward?
- Yes. Moving backward is called retrogression, and it happens when more people apply in a category than the annual limit allows, forcing State to pull the cut-off back to an earlier date. The Final Action Dates chart for this combination has retrogressed 15 times in the published record. The largest was in June 2014, when the cut-off moved back from 1 October 2012 to 1 January 2003 — 3,561 days, or about 9.8 years, in a single bulletin.
- When will a priority date in Other Workers become current for China (mainland-born)?
- Nobody can tell you that, and this site does not claim to. What can be measured is the pace: over the trailing published bulletins the Final Action Dates cut-off has advanced by an average of about 60.8 days per bulletin. The tool on this page projects the published cut-off of 1 May 2019 forward at that pace to estimate which bulletin would reach a given priority date. That is an estimate and assumes the pace holds. It is not a prediction and not a guarantee: cut-off dates routinely stall, and they can move backward without warning. This is not legal advice.
- Where does this Other Workers history come from, and how far back does it go?
- Every figure is the one the U.S. Department of State printed in its monthly Visa Bulletin, kept alongside the exact cell text it came from. This page carries 255 Final Action Dates bulletins back to January 2005. The Dates for Filing chart is not part of this bulletin's published source this month. The Visa Bulletin is a work of the U.S. Government and is in the public domain (17 U.S.C. section 105). 5 months are absent from the public record in that span (March 2009, September 2009, October 2009, November 2009, October 2012); they are shown as a break in the chart and are never filled in from a neighbouring month.
Source and method
Every figure on this page is read from the U.S. Department of State's monthly Visa Bulletin — the August 2026 edition for the current cut-offs, and each bulletin's own edition for the history. The Visa Bulletin is a work of the U.S. Government prepared by federal employees in the course of their duties, and is therefore in the public domain under 17 U.S.C. §105. This site is not affiliated with, endorsed by, or connected to the U.S. Department of State or any government agency.
This page carries 255 published cut-off cells and 130 recorded changes across the chart published for it this bulletin. Each cell is stored with the exact text State printed for it (the 01MAY19 shown above is the source's own), so every figure here is traceable back to the bulletin it came from.
5 months in the December 2001 to August 2026 span are absent from the public record — March 2009, September 2009, October 2009, November 2009, October 2012. They are recorded as gaps and shown as breaks in the charts above, never filled in from a neighbouring month.
Data version visa-bulletin-derived-v1 · 292 bulletins, December 2001 to August 2026 · Next monthly bulletin. The State Department publishes one bulletin per month, typically mid-month for the following month; past bulletins are immutable once published.